Wastewater land application projects that incorporate new or additional land application sites, and new or additional storage, treatment, or disposal systems are required to obtain site approval, facility plan/engineering report approval, and a construction/operation permit from the DNR. 

A land application operation permit will be issued along with the facility plan approval for projects without additional construction, and issued along with the construction permit for projects that require a construction permit. DNR review of land application projects is based on the Iowa Wastewater Facilities Design Standards, the Ten States Standards, applicable federal guidelines and standards, standard textbooks, current technical literature and applicable safety standards, Iowa Code Section 455B.174, and rule 567 IAC Chapter 64.

Back to top

Work Record Requests:

To initiate a land application project, submit a work record request to the Wastewater Engineering Section as an attachment in an email to wastewater-engineering@dnr.iowa.gov. Include "Work Request – Facility – Work Title" in the email subject line. An automated email response will be sent acknowledging DNR receipt of the work request.

Back to top

Construction Permit Applications

Applications for land application permits must be submitted to the DNR at least 120 days in advance of the construction and/or operation start date. The DNR will issue permits within 60 days of receipt of a complete application or deny the permit in writing unless a longer review period is required and the applicant is so notified.

Application Fee

Construction permit applications must be accompanied by a fee of $100. To make an electronic payment, proceed to https://programs.iowadnr.gov/payments and choose “Pay Wastewater Construction Permit Fee”. Fill the information on the form and follow the on-screen instructions.

Back to top

Land Application - Construction Permit Process Documents

Land Application - Construction Permit Process Documents
Form #   Document NameRevision
 Land Application Decision MatrixNew 9/18
 Process MapNew 6/17
 Land Application Permitting Process ManualUpdated 7/19
 Work Record Request 
Work Record Request
New 11/12
 Work Record Request InstructionsNew 11/12
542-0822Wastewater Land Application Checklist - Projects WITHOUT Construction PermitsNew 9/18
542-0821Wastewater Land Application Checklist - Projects WITH Construction PermitsNew 9/18
542-0820Land Application Site Survey ReportNew 11/18
 Sample Engineering ReportNew 9/18
542-0819Land Application Engineering Report Scope of Study ChecklistNew 9/18
Back to top

Land Application - Construction/Operation Permit Application Forms

Form #Document NameRevision
542-1253NPDES Application Fee Invoice for a New DischargerUpdated 7/23
542-3079Schedule Z: Wastewater Treatment and Disposal Systems Site SelectionNew 8/18
542-3080Schedule S: Wastewater Land ApplicationNew 8/18
542-3129Schedule A: General InformationUpdated 9/24
542-3099Schedule F: Treatment Project Site SelectionUpdated 11/15
542-3100Schedule G: Treatment Project Design DataUpdated 4/20
Form #Document NameRevision
542-0818Annual Monitoring ReportNew 9/18
Back to top

Emergency Land Application - Submit to DNR Field Office

Form #     Document NameRevision
 542-0899Application for an Operation Permit for Emergency Land Application of Wastewater New 8/18
Back to top

Land Application Resources

Form #Document NameRevision
 Loading EquationsNew 9/18
 Land Application Rate Calculator
Land Application Rate Calculator
New 9/18
542-0823Useful Web LinksNew 9/18