Wastewater land application projects that incorporate new or additional land application sites, and new or additional storage, treatment, or disposal systems are required to obtain site approval, facility plan/engineering report approval, and a construction/operation permit from the DNR.
A land application operation permit will be issued along with the facility plan approval for projects without additional construction, and issued along with the construction permit for projects that require a construction permit. DNR review of land application projects is based on the Iowa Wastewater Facilities Design Standards, the Ten States Standards, applicable federal guidelines and standards, standard textbooks, current technical literature and applicable safety standards, Iowa Code Section 455B.174, and rule 567 IAC Chapter 64.
Back to topWork Record Requests:
To initiate a land application project, submit a work record request to the Wastewater Engineering Section as an attachment in an email to wastewater-engineering@dnr.iowa.gov. Include "Work Request – Facility – Work Title" in the email subject line. An automated email response will be sent acknowledging DNR receipt of the work request.
Back to topConstruction Permit Applications
Applications for land application permits must be submitted to the DNR at least 120 days in advance of the construction and/or operation start date. The DNR will issue permits within 60 days of receipt of a complete application or deny the permit in writing unless a longer review period is required and the applicant is so notified.
Application Fee
Construction permit applications must be accompanied by a fee of $100. To make an electronic payment, proceed to https://programs.iowadnr.gov/payments and choose “Pay Wastewater Construction Permit Fee”. Fill the information on the form and follow the on-screen instructions.
Back to topLand Application - Construction Permit Process Documents
Form # | Document Name | Revision |
---|---|---|
Land Application Decision Matrix | New 9/18 | |
Process Map | New 6/17 | |
Land Application Permitting Process Manual | Updated 7/19 | |
Work Record Request Work Record Request | New 11/12 | |
Work Record Request Instructions | New 11/12 | |
542-0822 | Wastewater Land Application Checklist - Projects WITHOUT Construction Permits | New 9/18 |
542-0821 | Wastewater Land Application Checklist - Projects WITH Construction Permits | New 9/18 |
542-0820 | Land Application Site Survey Report | New 11/18 |
Sample Engineering Report | New 9/18 | |
542-0819 | Land Application Engineering Report Scope of Study Checklist | New 9/18 |
Land Application - Construction/Operation Permit Application Forms
Form # | Document Name | Revision |
---|---|---|
542-1253 | NPDES Application Fee Invoice for a New Discharger | Updated 7/23 |
542-3079 | Schedule Z: Wastewater Treatment and Disposal Systems Site Selection | New 8/18 |
542-3080 | Schedule S: Wastewater Land Application | New 8/18 |
542-3129 | Schedule A: General Information | Updated 9/24 |
542-3099 | Schedule F: Treatment Project Site Selection | Updated 11/15 |
542-3100 | Schedule G: Treatment Project Design Data | Updated 4/20 |
Form # | Document Name | Revision |
---|---|---|
542-0818 | Annual Monitoring Report | New 9/18 |
Emergency Land Application - Submit to DNR Field Office
Form # | Document Name | Revision |
---|---|---|
542-0899 | Application for an Operation Permit for Emergency Land Application of Wastewater | New 8/18 |
Land Application Resources
Form # | Document Name | Revision |
---|---|---|
Loading Equations | New 9/18 | |
Land Application Rate Calculator Land Application Rate Calculator | New 9/18 | |
542-0823 | Useful Web Links | New 9/18 |